Road works are scheduled to commence on Kirkham Road in Bowral from Monday, January 14.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
Works will include a full width rehabilitation of the road pavement, road widening and curve realignment.
In addition to the construction of the new concrete asphalt surface the adjacent road drainage will also be upgraded.
New safety signage, line-marking and raised pavement markers will also be installed.
These works will be carried out on a section of Kirkham Road between Sherwood Avenue and Mittagong Road.
Construction activities will be carried out between 7am and 6pm weekdays.
READ ALSO:
During construction sections of the road may be temporarily reduced to one-way traffic however the road will remain open to through traffic.
Road users are cautioned to follow the changed traffic conditions, exercise care when traveling through the work zones and be aware of loose stones and heavy machinery within the work areas.
Council thanks residents and motorists in advance for their cooperation and apologises for any temporary delays or inconvenience.
Works are expected to be completed by early May 2019. All timeframes are subject to weather conditions.
For further information please contact Jamil Ashraf from council’s infrastructure services branch on 4868 0519.