Hazardous materials unearthed during the renovation of Bowral Memorial Hall have required Wingecarribee Shire Council to allocate an additional $850,000 towards the restoration of the historic Bowral building.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
A report presented at the council's meeting of Wednesday August 17, 2022 detailed impacts necessitating an extension to the project's original delivery deadline and budget.
The discovery of asbestos and lead dust during construction were cited as major contributing factors to the project's reported variances. Additional structural issues found in the building's footings, concrete slab and roof were also detailed.
The report, which was subsequently adopted by the council, recommended allocating the additional funds to support the delivery of the project.
Administrator Viv May PSM said the budget extension was unfortunate but necessary.
"No one likes to see a variation to a forecast budget," he said.
"It is not however unusual to run into unforeseen issues when renovating a 138-year old building."
The initial forecast budget for the refurbishment project was $7.57 million.
Mr May said the unseasonal wet weather, COVID disruptions and shortage of skilled tradespeople had further exacerbated the restoration project.
"The council is pleased to report that the project team used the delays to re-examine and further fine-tune the project," he said.
"Together with input from key stakeholders they further modified the main stage design to better cater for unamplified music performances and improve performance acoustics.
"This will enable even more artists and guests to use and enjoy the finished hall.
"I'm confident that once renovations are complete Bowral Memorial Hall will be returned to its former glory and will be able to be enjoyed by residents and visitors for future generations."
Other improvements being carried out include the installation of a new roof and lifts, an upgrade of the kitchen and bathroom facilities and provision of access for all abilities. A new air conditioning system and sound and lighting equipment are also being included and the building's heritage faade is being protected and rejuvenated.
The refurbishment of Bowral Memorial Hall is anticipated to be completed by March 2023.
For more information on the refurbishment of Bowral Memorial Hall visit www.wsc.nsw.gov.au/Project-Directory/Bowral-Memorial-Hall-Refurbishment.
Our journalists work hard to provide local, up-to-date news to the community. This is how you can access our trusted content:
- Bookmark our website
- Follow us on Twitter
- Follow us on Google News
- Make sure you are signed up for our breaking news and regular newsletters